EXTENDED A507 CLOSURE & PARKING RESTRICTIONS

There are now to be two back-to-back closures of the A507 up to the A6, effectively turning into a 14-day closure starting on Monday, August 14.
⚫️August 14-17, 0900-1530 hours (due to be open overnight)
Pre-surface dressing/surface dressing/lining works
from A6 roundabout to approx 500m from the Flitwick Road, Maulden, roundabout.
⚫️August 18-28, complete 24hr closure
Full reconstruction of the carriageway
From A6 roundabout to Flitwick Road, Maulden, roundabout.
IN ADDITION THERE IS TO BE A PARKING SUSPENSION ON CLOPHILL ROAD, HALL END, MAULDEN, AUGUST 18-28
The suspension order covers Clophill Road from the A6 junction to the junction with the new section of Clophill Road.
The official diversion is as per the map, A6 A421, old A421, A507 and vice versa.
If you decide not to follow the official diversion and instead cut through the narrow lanes of Maulden, please do so with consideration and respect to residents and other road users.
REMEMBER:
⚫️It is the summer holidays so there are lots of children around.
⚫️It is a 30mph limit throughout the village.
⚫️It is not suitable for HGVs and there is a 7.5t weight limit.
⚫️The Limbersey Lane route may still be 60mph despite efforts to cut this limit but it is winding, very narrow, with numerous accesses from homes and farms, and the bends and dips catch unwary drivers off-guard particularly if the driver at speeds too fast for the road conditions.
⚫️Any other routes away from the official diversion – such as through Ampthill, Houghton Conquest, Haynes West End, Silsoe, Flitton & Greenfield, Wixams – deserve the same consideration and respect.